Thursday, September 8, 2011

Drainage Update

Number 7 is complete and we are working on #16 farway which should be completed today.  This area on #16 was not part of the original contract but we are slightly under budget on the other areas so we decided to add this area now rather than waiting until next year.  After today, we will need to sod all of the disturbed areas in the rough which will happen on Monday.  This will allow uninterrupted play of the full course on Friday.  The contractor will then return in mid-October to install slit drains on #8, #9, and #16 fairways. 